Upper Tamakoshi Hydel to be Ready by April 21, Power Production from mid-May

  1 min 22 sec to read
     Upper Tamakoshi Hydel to be Ready by April 21, Power Production from mid-May

April 8: The underconstruction Upper Tamakoshi Hydropower Project (456 MW) has reached final stage of construction. Major works such as intake, tunnel, transmission line, and substation have been completed.    
There are now minor civil and mechanical works going on under the project. Although one of the national pride projects was expected to be completed before the upcoming Nepali New Year (2078BS), it was delayed because of Covid-19 and some technical glitches.    
Lot-2 Hydro-mechanical contractor company has committed that the works as wielding and painting would be completed by April 21. Similarly, the installation of penstock pipe has been completed.    
Construction of embankment/intake, main tunnel, power house, tail race tunnel have also been completed.    
Executive Director at Nepal Electricity Authority and Chairperson of Upper Tamakoshi Hydropower Ltd, Hitendra Dev Shakya, conducted an inspection visit and held discussion with project officials, consultants and contractors on the schedule of releasing water to the tunnel with speedy completion of the remaining works.    
Shakya shared that power production would begin from mid-May. - RSS   
---  